Bridge In UK Demolished And Road Cleared Under 15 Hours

From the information we were able to gather, the Highways Agency and its contractors (Armac, the demolition company, and Costain-Carrillion JV, the main contractor) completed the demolition and the clearing of road just in 15.5 hours.
They closed the M1 motorway in Bedfordshire, and prepared it for the demolition of the old A5120 road bridge, built in 1959 and weighing over 1400 tonnes.
The demolition of the bridge kicked off at 9:15 pm on Saturday June 30, 2012. They worked throughout the night and the M1 was fully re-opened from 11:30 am the following morning.
You may also like: Second Niger Bridge To Be Completed In 2022
In this side of the world, it can take ages or several political tenures just to fill a pothole in a street. How long do you think it will take to do this same thing here in Nigeria?
If you’re interested, you can watch it on YouTube here.
-
Celebrities Auto1 week agoBillionaire Gifts Popular Bishop 2026 Rolls-Royce Cullinan And Over ₦370 Million Cash For Fuel
-
News1 week agoRare Bugatti Veyron 16.4 Grand Sport Vitesse ‘Jean-Pierre Wimille’ Sells For Record $5.44M
-
News1 week agoTop Luxury Car Brands 2026: Porsche Leads Brand Finance Ranking For 9th Consecutive Year
-
News1 week agoThere Will Be Several Variations Of The Lamborghini Temerario, Including Some Surprises
-
News1 week agoIt’s Not China’s Floating Cars: Moment Raging Floodwater Sweeps Tesla Away In Connecticut
-
News1 week agoSuzuki Wants To Cut Car Production Time By Half To Match Chinese Manufacturers
-
News1 week agoChina’s BYD Close To Overtaking Ford In European Sales
-
News1 week agoNext-Generation Ford Ranger Is In Development In Australia