Videos
Bridge In UK Demolished And Road Cleared Under 15 Hours

From the information we were able to gather, the Highways Agency and its contractors (Armac, the demolition company, and Costain-Carrillion JV, the main contractor) completed the demolition and the clearing of road just in 15.5 hours.
They closed the M1 motorway in Bedfordshire, and prepared it for the demolition of the old A5120 road bridge, built in 1959 and weighing over 1400 tonnes.
The demolition of the bridge kicked off at 9:15 pm on Saturday June 30, 2012. They worked throughout the night and the M1 was fully re-opened from 11:30 am the following morning.
You may also like: Second Niger Bridge To Be Completed In 2022
In this side of the world, it can take ages or several political tenures just to fill a pothole in a street. How long do you think it will take to do this same thing here in Nigeria?
If you’re interested, you can watch it on YouTube here.
-
Celebrities Auto6 days agoThrowback: When KC Luxury Boasted Of Being The Only Person In The World To Own Two Rare Mercedes-Maybachs
-
Celebrities Auto1 week agoInside KC Luxury’s Car Collection: From A ₦2.5B Brabus 800 Adventure XLP To Alicia Keys’ Former Maybach
-
News3 days agoAndrew Tate’s Lawyers Claim His Famous Bugatti And Aston Martin Are Rented
-
News1 week agoWho Is Herbert Wertheim? The 87-Year-Old Billionaire Who Bought The $40M Ferrari Luce “Chassis 0”
-
News6 days agoThe Tesla Cybercab Has Begun Transporting Passengers In Austin Texas
-
News1 week agoRM Sotheby’s Top 10 Best Sellers At Monterey Auction: From $40M Ferrari Luce To $34.65M McLaren F1 GTR
-
Autoshows & Awards1 week ago9 Coolest Cars Unveiled At The Quail: From Bugatti Destrier to Lamborghini Revuelto SV
-
News1 week ago2027 Mercedes C-Class Facelift Revealed With S-Class Tech & Grille