Bridge In UK Demolished And Road Cleared Under 15 Hours

From the information we were able to gather, the Highways Agency and its contractors (Armac, the demolition company, and Costain-Carrillion JV, the main contractor) completed the demolition and the clearing of road just in 15.5 hours.
They closed the M1 motorway in Bedfordshire, and prepared it for the demolition of the old A5120 road bridge, built in 1959 and weighing over 1400 tonnes.
The demolition of the bridge kicked off at 9:15 pm on Saturday June 30, 2012. They worked throughout the night and the M1 was fully re-opened from 11:30 am the following morning.
You may also like: Second Niger Bridge To Be Completed In 2022
In this side of the world, it can take ages or several political tenures just to fill a pothole in a street. How long do you think it will take to do this same thing here in Nigeria?
If you’re interested, you can watch it on YouTube here.
-
Auto Sport1 week agoYangwang U9 Xtreme, Bugatti Chiron Super Sport 300+: Top 10 Fastest Cars In The World Ranked By Top Speed
-
Car Comparison1 week agoChina’s Hongqi N701 vs US ‘The Beast’: How Xi Jinping and Donald Trump’s Armored Limos Compare
-
News1 week agoThree Pagani Icons—Zonda, Huayra And Utopia—Gather To Celebrate 140 Years Of Mercedes-Benz
-
Celebrities Auto1 week agoAtiku Blasts ‘Wastage’ Over First Lady’s Reported ₦1bn Gift Of 7 Toyota Prados To APC Youth Leaders
-
News1 week agoThe EU Is Planning A Fresh Driver Crackdown: Fuel Tanks In New Cars Might Get Even Smaller
-
News1 week agoWhat Does The Lexus RX 350’s “RX” Actually Mean?
-
News7 days agoBMW Group Moves One Million Vehicles Without Drivers Across Four Production Plants
-
Celebrities Auto1 week agoNollywood Actor Okunnu Inspects Stunning ₦600 Million Range Rover SV In Canada